Ny utsettelse....

http://www.newsweb.no/newsweb/search.do?messageId=431748

"In line with the project progression on site, the first gas was expected to be
transported in July 2017 under the reconfirmed agreements of 24 May 2017 and 1
June 2017. Financial close under the agreements has been pending completion of
the full package of project agreements, which in turn been reliant on
finalization of all relevant government approvals. We are confident that our
client is able to obtain these Government approvals. However, these transactions
are located in Africa where such commercial deals are prone to prevarications
and delays. In anticipation of these approvals the commissioning for "first gas"
has been deferred and we expect financial close to occur in August rather than
in July and with the results that our ships will load first LNG for the client
in August."